ATTRIBUTE DESCRIPTORS VS MATUR TY SCORE | |||||||
| Schedule | Cost | Requirements | Technical Understanding | Technical Difficulty | Commercial | Operation and Support |
DELIVERING THE DMO ACQUISTION PROJECT (Delivery Performance) | |||||||
Maturity Score | How are the IMR | How well is the cost | How well are | Defence's understanding of the | How well are the | How well is industry performing? | How well prepared |
10 | Achieved | Proven | Demonstrated | Fully Understood | Proven | All Delivered | Operational |
9 | Confident | Contingency Remains | Tested | Transferred | Tested | Delivered | Transitioning |
8 | Acceptable | Confident | Designed | Arranged | Integrated | Delivering | Integrated |
7 | In Tolerance | Within Contingency | Acceptable | Needs Understood | Designed | Manages Risk | Being Procured |
6 | Manageable | Negotiated | Contracted | Provided for | Planned | As Contracted | Defined |
DEFINING THE DEFENCE PROJECT (Process Maturity) | |||||||
Maturity score | How realistic is | What is the quality of | How well are the requirements | How well are the solutions understood? | How difficult is to | Can industry deliver the | Is the impact on |
5 | Confirmed | Pre- Endorsed capability | Endorsed | Understood | Manageable | Offered | Planned |
4 | Understood | Industry Tested | Documented | Feasible | Feasible | Industry Proposals | Known |
3 | Feasible | Reasonable | Solution Classes | Coalescing | Building Blocks | Strategy Developed | Issues Understood |
2 | Drivers known | Plausible | Scenarios identified | Minimal | Conceptual | Possible | Conceivable |
1 | Speculative | Speculative | Deficiency | Not at all | Not Defined | Not Yet | Not Identified |
Project Life Cycle Gates CDG_Responsibility DMO_Responsibility | Represents | Benchmark Maturity Score |
Enter Defence Capability Plan | The stage at which a project is recommended to Government for inclusion in the Defence Capability Plan | 13 |
Decide Viable Capability Options | The stage in the capability definition/ development process when 1st Pass options that will be put to Government are decided by CCDG | 16 |
1st Pass Approval | The stage at which 1st Pass options to be put to Cabinet are endorsed by the DCC | 21 |
Industry Proposals/ Offers | The stage at which formal responses from industry to an RFP or RFT have been received and evaluated | 30 |
2nd Pass Approval | The stage in the capability definition/ development process when 2nd Pass Approval is sought from Cabinet | 35 |
Contract Signature | On completion of contract negotiations and on concluding contract signature of a contract that has maximum influence on the project. | 42 |
Preliminary Design Review(s) | On completion of System Requirements Reviews and when Preliminary Design Reviews are completed | 45 |
Detailed Design Review(s) | On completion of Detailed Design Reviews | 50 |
Complete System Integration and Test | On completion of Verification and Validation activities at the system and subsystem levels | 55 |
Complete Acceptance Testing | On completion of all contractual acceptance testing and associated testing activities nominated in the TEMP | 57 |
Initial Materiel Release (IMR) | Occurs when the materiel components that represents the DMO contribution to Initial Operational Release (IOR) are ready for transition to the Capability Manager | 60 |
Final Materiel Release (FMR) | Occurs when all the products and services within the MAA have been transitioned to the Capability Manager. | 63 |
Final Contract Acceptance | On Final Acceptance as defined in the contract | 65 |
MAA Closure | Occurs when all of the actions necessary to finalise the MAA have been completed, including completion of all financial transactions and records, completion of contracts and transfer of remaining fund. | 66 |
Acceptance Into Service | The point at which the Capability Manager accepts the Materiel System, supplies and services for employment in operational service223 | 67 |
Project Completion | Project closure is achieved when the project is financially closed, support arrangements have been transitioned and all MAA requirements have been demonstrated and transitioned. | 70 |
___________________________________________________________________________
223 Where multiple elements of a mission system are involved (e.g. 3 surface combatants) this date represents Initial Operational Capability (IOC) of the initial Subset, including its associated operational support, i.e. when the Initial Operational Capability is achieved. (DI(G) OPS 45-2 refers).