Minimum Works Requirements

1.11  The Contractor shall ensure that the Works comply with Good Industry Practice, relevant statutory requirements and Consents including, but not limited to, the following:

a)  British Standards, Codes of Practice, or equivalent European industry recognised standards and guidance;

b)  Health and Safety at Work Executive guidance notes;

c)  The Authority's Policies;4

d)  Requirements of the utilities companies;

e)  Building Research Establishment Digest Recommendations;

f)  Fire safety requirements in agreement with the fire authority; and

g)  Relevant Environmental Agency guidance notes, consents and authorisations.

1.12  The Contractor shall provide materials, equipment, plant, machinery and other goods of sound and satisfactory quality and fit for purpose for which they will be used. All workmanship and manufacture of fabrication shall meet or surpass all relevant British or EU standards or equivalent.




___________________________________________________________________________________________

4  The  Authority is to state relevant policies, if any.