1.19 The Contractor shall be responsible for identifying and undertaking all enabling works necessary to ensure the Site(s) is suitable for the development of the Works.
1.20 The Contractor shall carry out all demolition of existing structures and make safe redundant infrastructure on the Site(s) in accordance with BS6187:2000.
1.21 The Contractor shall be responsible for undertaking remediation or removal of any contaminated waste, material or land.
1.22 The Contractor shall carry out any protection and diversion works associated with any existing infrastructures located on the Site(s) required for the construction of the Works and ensure continuity of utility supplies to any Adjoining Properties in so-far as they may be affected by the Works. This shall include but is not limited to gas, electricity, water, sewerage and communications services.
1.23 The Contractor shall ensure that adequate retaining walls and/or support to excavated faces are provided to support any Adjoining Property during the carrying out of the Works.
1.24 The Contractor shall ensure the Site(s) (and any Works carried out outside the Site(s)) is safe and secure throughout the period up to the Readiness Date and shall ensure no unauthorised access to the Site(s).
1.25 The Works shall be suitably housed and protected such that waste delivery vehicle operators, Authority Representative, Authority staff or visitors cannot gain access to areas or parts of the Site(s) that could cause harm or a risk to their health and safety.