1.36  The Contractor shall minimise nuisance and environmental impact during construction and shall design and construct the Works so as to minimise nuisance and environmental impact including but not limited to the impact of:

a)  light;

b)  noise;

c)  vermin and other pests;

d)  litter;

e)  flies;

f)  dust;

g)  emissions;

h)  odour; and

i)  traffic.

1.37  The Contractor shall ensure that all construction vehicles leaving the Site(s) are adequately cleaned to prevent the deposit of waste material and debris on any Adjoining Property. If such material or debris is so deposited the Contractor shall employ such measures as shall be necessary to remove the material and debris and to clean and reinstate such Adjoining Property to the reasonable satisfaction of the owners or occupiers of the Adjoining Property.