1.46 The Contractor shall develop and maintain a detailed Construction Programme covering all elements of the Works and based on the Construction Programme included in the relevant Method Statement.
1.47 The Contractor shall submit to the Authority the Construction Programme and any subsequent amendment to the Construction Programme within [ ] Business Days of its amendment and adoption for the Works.
1.48 The Contractor shall carry out the Works in accordance with the Construction Programme.
1.49 The Contractor shall monitor and report to the Authority on a monthly basis progress of the Work against the latest revision of the Construction Programme.