Construction Phase Reporting

1.50  The Contractor shall submit to the Authority within [  ] Business Days following the end of a month, a Monthly Construction Progress Report covering the construction activities carried out in the proceeding month.  The Monthly Construction Progress Report shall include as a minimum a description of the following:

a)  Assessment of actual progress by comparison to the submitted Construction Programme;

b)  Progress with obtaining Consents;

c)  Progress with discharging any requirements of the Consents;

d)  Report on any material risk to achieving the Planned Service Commencement Date; and

e)  Where the Monthly Construction Progress Report covers the period in which the Readiness Test Certificate is issued, the Monthly Construction Progress Report shall include a copy of the Readiness Test Certificate.