1.50 The Contractor shall submit to the Authority within [ ] Business Days following the end of a month, a Monthly Construction Progress Report covering the construction activities carried out in the proceeding month. The Monthly Construction Progress Report shall include as a minimum a description of the following:
a) Assessment of actual progress by comparison to the submitted Construction Programme;
b) Progress with obtaining Consents;
c) Progress with discharging any requirements of the Consents;
d) Report on any material risk to achieving the Planned Service Commencement Date; and
e) Where the Monthly Construction Progress Report covers the period in which the Readiness Test Certificate is issued, the Monthly Construction Progress Report shall include a copy of the Readiness Test Certificate.