1.51 The Contractor shall provide the Authority, a set of As-Built Drawings on the earlier of the date falling [ ] Business Days after the date they become available to the Contractor or within [ ] months after the date of issue of the Readiness Test Certificate in respect of the Facility.
1.52 The Contractor shall promptly update the As-Built Drawings supplied to the Authority to reflect any changes from time to time and promptly provide a set of such amended As-Built Drawings to the Authority.