2.1 The Contractor shall develop an outline Testing and Commissioning Plan based on the Testing and Commissioning Plan included in the relevant Method Statement. The detailed Testing and Commissioning Plan shall be no less onerous than that included with the relevant Method Statement.
2.2 The Contractor shall submit to the Authority as a Reviewable Item the detailed Testing and Commissioning Plan as a minimum [ ] Contract Months prior to the Planned Readiness Date. The Commissioning Plan shall include but not be limited to the Contractor's proposals for:
a) cold commissioning of individual Equipment and Facilities;
b) the process to achieve the Readiness Test;
c) hot commissioning of the Works including the incremental acceptance, processing and treatment of Contract Waste; and
d) the Acceptance Tests.
2.3 The Contractor shall carry out the commissioning in accordance with the Testing and Commissioning Plan.
2.4 Prior to the issuance of the Readiness Test Certificate, the Contractor shall carry out commissioning of the Works to demonstrate that the design construction installation and plant performance:
a) comply with health and safety Legislation and guidance;
b) comply with manufacturers requirements;
c) are suitable for testing their integration within the Works;
d) are fit for their intended purpose; and
e) are capable of meeting the requirement of PR2.
2.5 After the issuance of the Readiness Test Certificate, the Contractor shall carry out commissioning of the Works to demonstrate that their design, construction, installation and plant performance:
a) comply with health and safety Legislation and guidance;
b) comply with manufacturers requirements;
c) are suitable for integration within the Works;
d) are fit for their intended purpose; and
e) the requirements of PR3.