Commissioning Phase Reporting

2.6  The Contractor shall submit to the Authority within [ ] Business Days following the end of each Contract Month during the Commissioning Phase, a Monthly Commissioning Progress Report covering all the commissioning and testing activities carried out in the preceding Contract Month. The Monthly Commissioning Progress Report shall include as a minimum a description of the following:

a)  Assessment of actual progress by comparison to the submitted Commissioning Programme; and

b)  Summary of the commissioning tasks in the following monthly period.