3.2 The Contractor shall develop, maintain and update monthly an Environmental Impact Control Plan included in the relevant Method Statement.
3.3 The Environmental Impact Control Plan shall include all procedures and actions required by the Contractor to:
i) minimise the environmental impacts of transporting, receiving, treating and disposing of Contract Waste and Third Party Waste including but not limited to the impacts from:
a) light;
b) noise;
c) vermin and other pests;
d) litter;
e) flies;
f) dust;
g) emissions;
h) odour; and
i) traffic.
ii) to meet the environmental conditions contained or referred to within the Consents;
iii) to meet all Legislation; and
iv) where, practical, minimise amenity impacts on the local population, with respect to the Site(s) and all Contractor operations and activities external to the Site(s).
3.4 The Contractor shall comply with the latest version of the Environmental Impact Control Plan.
3.5 The Contractor shall implement at its own cost the amendments to the Environmental Impact Control Plan including for the avoidance of doubt all changes required to the Facilities and Services.
___________________________________________________________________________________________
9 Authorities may consider that the issues dealt with in the Environmental Input Control Plan are dealt with in the Consents required for the operation of the Facility and regulated by the Environment Agency. If so, this provision may be deleted.