3.6 The Contractor shall develop and agree with the Authority a Contingency Plan that identifies how the Services will be provided in the event that the Authority is required to deliver Contract Waste to a Contingency Delivery Point on a permanent or temporary basis or during emergency situationsThe Contingency Plan shall include:
(i) Location(s) of Contingency Delivery Point(s);
(ii) Arrangements for the redirection of Contract Waste to Contingency Delivery Point(s); and
(iii) Details of any impact on the Services as a result of using the Contingency Delivery Point(s).
The first Contingency Plan shall be delivered to the Authority [ ] months prior to Service Commencement.
3.7 The Contractor shall submit any proposed changes to the Contingency Plan to the Authority in accordance with the Review Procedure.
3.8 The Contractor shall notify the Authority prior to implementing the Contingency Plan.
3.9 The Contractor shall provide an updated Contingency Plan to the Authority within [ ] days of a change agreed pursuant to paragraph 3.7.
3.10 The Contractor shall confirm within [ ] days of each Contract Year that the Contract Plan is up to date.
3.11 The Contractor shall ensure that the ground within [ ] metres of the boundary of each Site(s), including but not limited to access roads and adjoining land to which the Contractor can lawfully obtain access without payment of monies, are kept free from litter and fly tipped waste.
3.12 Where waste referred to in paragraph 3.10 above is brought to the attention of the Contractor by the Authority then:
a) within [ ] minutes of being notified the Contractor shall, contain and control such waste with consideration to its health and safety obligations; and
b) within [ ] hours the Contractor shall remove and dispose of the litter or fly-tipped waste and clean up any affected surrounding area.
3.13 The Contractor shall remove from the Site(s) and transport all Contract Waste in accordance with the relevant Method Statement.
3.14 The Contractor shall only store Contract Waste in designated on-Site(s) storage Facilities.