Final Disposal

3.71  Final disposal shall be provided for all process residues and rejects that cannot otherwise be Recycled, Composted or Recovered.

3.72  The Contractor shall ensure that adequate landfill capacity exists for all process residues and rejects for the term of the Contract.

3.73  The Contractor shall supply the Authority with full details of the landfill site(s) to be used and copies of all Necessary Consents.  

3.74  The Contractor shall agree with the Authority any proposed changes or substitution of landfill sites in accordance with clause 32 of the Contract, and update the Service Delivery Plan accordingly.