PR4: Handback Requirements.

Performance Standard Ref

Performance Standard

Rectification Category (ref: Table 1)

Monitoring Frequency (ref: Table 2)

Performance Standard Monitoring Methodology

Performance Deduction Category

4.1

The Contractor has developed a Handback Plan as required in the Handback Requirements.

[4]

PO

Receipt of Handback Plan within the stated timescale.

[E]

4.2

The Contractor has included a Handback programme within the Handback Plan.

[4]

PO

Receipt of the Handback Plan as part of the Handback Plan within the stated timescale.

[E]