| Variables | Observations | Default Value/Range | |
|
|
| Stage 2 | Stage 1 |
| 29. Initial CapEx Period Payment | Generally, waste projects start generating a unitary charge from project start date, as the Contractor assumes immediate responsibility for the existing waste management services and will be paid by the Authority. The unitary | N/A | {70}% |
|
| charge payable is however likely to be less during the period prior to full operations, when the main construction works are undertaken. This reflects the fact that existing services will be commissioned whilst new infrastructure is developed. The average level of unitary charge payable during the period prior to full operations payable during the first year of full operations should be entered here. This should be expressed as a percentage of the full unitary charge payable during the first year when the facility is fully operational. |
|
|