Table 1 Procurement Efficiency Weightings  PROCUREMENT EFFECTIVENESS INDEX

 

Nominal Ratings

1655v1

Weight

In-House

Traditional

Alliances

Outsourcing

BOOT

PPP

NPV Investment

10

0.0

1.0

0.0

7.5

10.0

9.0

Specification Form

10

0.0

1.0

5.0

10.0

7.5

10.0

Innovation & technology

10

0.0

2.0

5.0

8.0

6.5

10.0

Integrate design & construct

10

0.0

0.0

7.5

7.5

10.0

10.0

Risk transfer

10

2.5

2.5

5.0

10.0

10.0

10.0

Certainty (lifecycle costing)

10

0.0

0.0

2.0

8.0

8.0

10.0

Value for Money

60

2.5

6.6

24.5

51.0

52.0

59.0

Delivery performance

5

1.5

1.5

4.0

5.0

5.0

5.0

Investment utility

5

0.0

0.0

1.0

5.0

5.0

5.0

Sustainability principles

5

5.0

5.0

4.0

2.0

2.0

4.0

Incentive

15

6.5

6.5

9.0

12.0

12.0

14.0

Quality services

10

3.0

2.5

2.5

5.0

7.5

10.0

Outcomes

10

3.0

2.5

2.5

5.0

7.5

10.0

Cost

5

3.0

3.0

1.5

4.0

2.5

1.5

Time

5

3.0

3.0

2.0

2.5

2.5

1.5

Project size

2

2.0

1.0

0.0

2.0

1.0

0.0

Collaboration/ADR

3

0.0

0.0

3.0

0.0

0.0

3.0

Process

15

8.0

7.0

6.5

8.5

6.0

6.0

 

 

 

 

 

 

 

 

Total Rating

100

20.0

22.5

42.5

76.5

77.5

89.0

Source: Bond University 2008