Table 5 Project Risk Areas
Project Risk Type Description | ||
Procurement | Complexity of Contract Structure | Where the complexity of the contract structure is likely to result in a delay to the contract being signed or impact on works duration, costs and benefits achieved. |
Late Contractor Involvement in Design | Where the late involvement of the contractor in the design is likely to lead to redesign or problems during construction. | |
Contractor Capabilities | Where the contractor's capabilities/experience of managing projects of a similar nature is likely to impact on his ability to perform the works programme on schedule and/or to the required quality. | |
Government Guidelines | Where existing government guidelines for procurement may not provide the Client with the necessary guidance to procure adequately. | |
Dispute and Claims Occurred | Where disputes and claims are likely to occur if no mechanisms exist to manage effectively adversarial relationships between project stakeholders. | |
Information management system | Where effective information management and communication methods are essential to enable the delivery of the project. | |
Other (specify) | Where other influencing factors that relate to procurement are likely to affect the project outcome. | |
Project Specific | Design Complexity | Where the complexity of design (including requirements, specifications and detailed design) is such that it needs significant management to reduce the impact on project outcomes. |
Degree of Innovation | Where the degree of innovation required due to the nature of a project requires unproven methods to be used to deliver the project. | |
Environmental Impact | Where the nature of the project has a major impact on its adjacent area where there is a strong likelihood of objection from neighbours and the general public. | |
Others (specify) | Where other project specific influencing factors are likely to affect the project outcome. | |
Client Specific | Inadequacy of the Business Case | Where project scope changes are likely to occur as a result of the poor quality of requirement specifications and inadequate project scope definition. |
Large Number of Stakeholders | Where project scope changes are likely to occur as a result of conflicting requirements or bad co-ordination of project stakeholders. | |
Funding Availability | Where project delays or changes in scope are likely to occur as a result of the availability of funding (i.e. departmental budget spent or insufficient contingency funds). | |
Project Management Team | Where the Client project management team's capabilities/experience of managing projects of a similar nature is likely to impact on the project outcome. | |
Poor Project Intelligence | Where the quality of initial project intelligence (e.g. preliminary site investigation, user requirements surveys, etc) is likely to have a significant impact on the likelihood of the occurrence of unforeseen problems. | |
Others (specify) | Where other Client specific influencing factors are likely to affect the project outcome. | |
Environment | Public Relations | Where a high level of effort is required to address public concern about the project, which may have a significant impact on the project outcomes. |
Site Characteristics | Where the characteristics of the proposed environment for the project are highly sensitive to the project's environmental impacts (e.g. Greenfield site with badger setts, or contaminated brownfield site). | |
Permits / Consents / Approvals | Where there is a likelihood of significant delays obtaining necessary permits, consents or approvals. | |
Others (specify) | Where other influencing factors that relate to the proposed environment for the project are likely to affect the project outcome. | |
External Influences | Political | Where the project outcomes are sensitive to political influences. |
Economic | Where the project outcomes are sensitive to economic influences. | |
Legislation / Regulations | Where the project outcomes are sensitive to legislation and regulation changes. | |
Technology | Where the project outcomes are sensitive to technological advancements. | |
Others (specify) | Negative influencing factors that are external to the project that have an impact that are not identified above. |
_____________________________________________________________________________________________________
11 Each identified project risk area has a negative impact on the delivery of a project in terms of time delays, costs overruns and benefit shortfalls as described