1. Complexity of Contract Structure
• Details of risk transfer had to be clarified
• Payment mechanism had to be defined
• Unforeseen amount of negotiation required on terms of contract
2. Late Contractor Involvement in Design
• Value management was necessary but contractor was not involved early enough to allow for it
• The design could not be built due to construction problems (e.g. access)
• Contractor provided design / construction feedback at a late stage resulting in a redesign
3. Poor Contractor Capabilities
• Contractor was inexperienced
• Site health and safety standards were not met
• Construction was not carried out to the necessary standards
• The contractor had insufficient resources
4. Government Guidelines
• No precedent or guideline had been developed to procure a leading edge project
5. Dispute and Claims occurred
• Dispute over interim payments
• Claims for changes in scope
• Claims for late release of information by other stakeholders
6. Information Management Systems
• The interfaces between the stakeholders were not managed efficiently resulting in information
not being transferred effectively.