| Recorded Optimism Bias (%)16 | Non-standard Civil Engineering | Standard Civil Engineering | |||||||
| 15 | 66 | - | 5 | 34 | 44 | - | - | ||
| Capital Expenditure | Operating Expenditure | Capital Expenditure | Operating Expenditure | ||||||
| Risk Area Contributions to Recorded Optimism Bias (%)17 | Non-standard Civil Engineering | Standard Civil Engineering | |||||||
| Procurement | Complexity of Contract Structure | 2 | 9 | - | 3 | - | - | ||
| Late Contractor Involvement in Design | - | 5 | - | - | |||||
| Poor Contractor Capabilities | 2 | 6 | - | 14 | - | - | |||
| Government Guidelines | - | - | - | ||||||
| Dispute and Claims Occurred | 18 | - | 31 | - | - | ||||
| Information management | 1 | 3 | - | - | - | ||||
| Other (specify) | 1 | 1 | - | 4 | - | - | |||
| Project Specific | Design Complexity | 5 | 3 | - | 12 | - | - | ||
| Degree of Innovation | 15 | 7 | - | 12 | - | - | |||
| Environmental Impact | 2 | - | - | - | |||||
| Other (specify) | - | 1 | 58 | 39 | - | - | |||
| Client Specific | Inadequacy of the Business Case | 10 | 39 | - | 5 | - | - | ||
| Large Number of Stakeholders | - | - | - | ||||||
| Funding Availability | 2 | - | 17 | 5 | - | - | |||
| Project Management Team | 1 | 4 | - | - | - | ||||
| Poor Project Intelligence | 3 | 4 | - | 15 | 10 | - | - | ||
| Other (specify) | - | - | - | ||||||
| Environment | Public Relations | - | - | - | |||||
| Site Characteristics | 2 | - | 8 | 5 | - | - | |||
| Permits / Consents / Approvals | - | - | - | ||||||
| Other (specify) | - | - | - | ||||||
| Political | - | - | - | ||||||
| Economic | 27 | 1 | - | 33 | 10 | - | - | ||
| External Influences | Legislation / Regulations | 1 | 3 | - | 2 | - | - | ||
| Technology | 7 | 1 | - | - | - | ||||
| Other (specify) | 5 | 12 | - | 11 | - | - | |||
- No information was available
_____________________________________________________________________________________________________
16 This table should not be used for calculating optimism bias levels for current projects.
17 Contributions from each project risk area are expressed as a % of the recorded optimism bias. Note: The sum of individual percentages contributions in each column may not add up to 100% due to rounding errors.