41 Ninety four per cent of projects responding to our 2008 survey were reported to have been delivered on, or less than five per cent over, price. The remaining six per cent reported price increases of five per cent and over. One project reported delivery at less than the contracted price, which was because of public sector initiated changes which reduced the price (Figure 8).
Figure 8 |
Price to public sector compared to PFI contract |
|
Source: National Audit Office |
NOTE |
1 Statistics are based on 91 respondents (23 additional 2008 respondents were unable to provide these data). |