In this part of the P3 business case, the project sponsor should:
• Disclose general and project specific objectives for the project, including the process used by the sponsor to develop the objectives and go-forward process for measuring the achievement of the objectives;
- General objectives relate to the sponsors overall policy, political, environmental, economic, social or technological environment. Project-specific objectives relate to the sponsor's desired outcomes from the project only.
• Describe and substantiate the economic, social, environmental, and other benefits related to the achievement of the general and project specific objectives. A process for measuring the benefits should also be disclosed; and
• Where possible, describe the objectives and benefits in both qualitative and quantitative terms.