5.00  Equipment Risk (F.F. &E.)

5.00  Equipment Risk (F.F. &E.)- The cost base for this category is the equipment value, which is not included in the contract

5.01

Owner Procurement / Project Co.

Risk that equipment procured by the Owner is not suitable for the required use, or is not delivered in compliance with the construction contractor's schedule.

5.02

Equipment Selection Changes

Risk that there are changes to the selected equipment by the Owner resulting in delays and additional costs for the construction contractor.