5.00 Equipment Risk (F.F. &E.)- The cost base for this category is the equipment value, which is not included in the contract | ||
5.01 | Owner Procurement / Project Co. | Risk that equipment procured by the Owner is not suitable for the required use, or is not delivered in compliance with the construction contractor's schedule. |
5.02 | Equipment Selection Changes | Risk that there are changes to the selected equipment by the Owner resulting in delays and additional costs for the construction contractor. |