6.00 Permit and Approvals - The cost base for this category is the construction and design portion of the contract value | ||
6.01 | Municipal Approvals | Risk that municipal approvals delay commencement of construction. |
6.02 | Building Permits | Risk that there is a delay in providing the Building Permit to the construction contractor and this results in an extension of time for the construction contractor with resultant additional costs. |
6.03 | Other Permits | Where Other Permits are to be obtained by the Owner; then any delay in providing those Permits to the construction contractor would result in an extension of time for the construction contractor with resultant additional costs. |
6.04 | Building Code Design | The risk that the design does not meet current building code. |
6.05 | Building Code Construction | The risk that construction does not meet current building code. |
6.06 | Utilities Company Fees | The risk that Utility Company fees are not included in the contract sum. The contract documents should clearly state which party is to include for utility company fees. |
6.07 | Title/Access/Title Encumbrances | Risk that the construction contractor does not comply with all the encumbrances associated with the site. |