| Risk Category | Cost Base | Risk Retained by Province at Average Impact | |||
| Design Build Finance & Maintain | Traditional Model Model | ||||
| 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 | Policy / Strategic Design & Tender Site Conditions/Environmental Construction Equipment Risk (F.F.&E.) Permit and Approvals Completion Commissioning Life Cycle and Residual Risk Operational Project Agreement | Total Contract Design & Construction Design & Construction Design & Construction F.F.&E. (outside of contract) Design & Construction Design & Construction Maintenance Operations Operations Total Contract | 5.6% 1.7% 1.1% 1.4% 0.0% 0.0% 0.1% 46.1% 0.3% 1.0% | 20.4% 19.4% 1.1% 16.6% 0.8% 0.2% 0.7% 132.8% 51.5% 0.0% | |
| Total Risks Retained by Province | Total Contract | 16.2% | 76.5% | ||