2.37 In cases where the authority decides to withdraw a request for a change in service (other than as a result of a contractor failure), particularly after a first stage approval has been given for a high value change, costs will only be reimbursed if a budget for these third party costs has been agreed and where the SPV demonstrates that the expenditure has incurred The budget should not be exceeded without prior permission of the authority.