• During the bidding phase, the public sector selected an alternative and more expensive tunnel route proposed by the Cross City Motorway consortium. As there was no additional public funding available, these additional costs were planned to be recovered through higher tolls.
• The government committed to close a number of surface roads, thereby "encouraging" people to use the tunnel.