LESSONS LEARNED

•  The concession has been structured so that the public authorities benefit not only from an upfront receipt but will also share in the future success of the port.

•  The financing arrangements were structured to ensure that the financing risk sat with the concessionaire yet the project could still benefit from tax-exempt debt rather than using commercial bank debt.