An estimate of the cost of each risk should be made

The focus on risk underpins the financial analysis of a project or opportunity because each risk should be allocated a theoretical cost. In reality, however, this cost is likely to be a range of estimates rather than a point estimate. The simple calculation is shown in the following equation:

Expected cost of risk = probability of risk occurring × cost if risk occurs

It is this calculation of the expected cost of risk that makes the discrimination between risk and uncertainty important: it is easier to put a price on risks but can be very difficult, if not impossible, to put a price on uncertainty.



Table 1: Impact of various risks and uncertainties

 

Risk

Uncertainty

Factor

Variable impact: Impact can be positive or negative and can change over time.

Binary impact:
Impact happens or it does not. Assumes impact is negative.

Variable impact: Impact can be positive or negative and can change over time.

Binary impact:
Impact happens or it does not.Assumes impact is negative.

Technical

•  Capital costs differ from those forecast

•  Operational costs, including maintenance, differ from those
forecast

•  Price of inputs- e.g., feedstock

•  Contract effectiveness (the private-sector party is not left with any it thought had been passed on to another party)

•  Construction completion is late

•  Technology performs differently from the way it was forecast

•  Technology does not work as expected

Markets

•  Revenue risk if linked to performance

 

•  Revenue risk if linked to demand

•  Force majeure

Performance of obligations under the contract

 

•  Failure to achieve required operational performance

 

 

Financial / Economic

•  Cost of debt

•  Exchange rate

•  Interest rate

•  Debt margin (either bank or capital markets)

•  Inflation/deflation

•  Cost of insurance

 

•  Availability of debt

•  Market failure

•  Unavailability of insurance

Political consequences

 

 

•   Political interference

•  Change of law, either general or specific to sector

•  Legal and regulatory enforcement

•  Expropriation

•  Political interference

•  Currency convertibility

Other

 

 

•  Procurement process:

-duration and

-competition

•  Counterparty failure

•  Land acquisition

•  Climate change- e.g., flooding