Evaluating Responses

4.13  The project timetable should allow adequate time for the evaluation of PQQ responses. This should be undertaken jointly by the Authority and the Project Company in accordance with pre-agreed criteria. A shortlist of organisations to receive Invitations to Tender (ITT) should then be agreed