Table 1.C: Estimated payments (in nominal terms, undiscounted) under PFI contracts - signed projects (£m)

 

Unitary charges

 

 

2011-12
2012-13
2013-14

2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30

8,568
9,115
9,561
9,722
9,803
9,770
9,874
9,456
9,620
9,683
9,531
9,407
9,394
9,556
9,525
9,285
9,200
9,106
8,805

 

 

2030-31 2031-32 2032-33 2033-34 2034-35 2035-36 2036-37 2037-38 2038-39 2039-40 2040-41 2041-42 2042-43 2043-44 2044-45 2045-46 2046-47 2047-48 2048-49

8,251
7,770
7,313
6,657
6,066
5,239
4,619
3,942
3,631
2,912
2,223
1,639
1,212
677
565
260
267
274
20

Figures based on departmental and Devolved Administration returns.