B.  The level of the EU grant is determined by the level of eligible expenditures

The eligible expenditure is the key basis for the calculation of the level of Community assistance. This calculation depends on the type of project:

For non-revenue generating projects:

The level of grant is calculated by applying the co-financing rate to the total of eligible costs25.

For revenue generating projects:

The funding-gap26 method will be applied.




__________________________________________________________________________________

25  The co-financing rate, defined as the percentage of total eligible costs that can be co-financed by the EU grant, is set by priority axis in every operational programme.

26  The funding-gap method is defined in article 55 of the General Regulation. It is also clearly explained in the Commission Working Document No.4 "Guidance on the methodology for carrying out Cost-Benefit analysis" and in COCOF 07/0074/04-EN. Further guidance is available in JASPERS's Working paper "Combining EU Grant Funding with PPP for Infrastructure: Conceptual Models and Case Examples".