Programme Roads |
| Forward timeline |
Highways Agency programme in construction (pre-2010 Spending Review) |
| • Programme on track: • M25 J16-23 completion 2012 • M25 J27-30 completion 2012 • A46 Newark to Widmerpool completion 2012 • M1 J10-13 completion 2013 |
Highways Agency managed motorways programme - 2010 Spending Review projects |
| • Programme on track |
Highways Agency trunk road improvements programme - 2010 Spending Review projects |
| • Existing schemes on track: A11 Fiveways start of works 2012-13; A556 Knutsford start of works 2013-14 or 2014-15 |
Highways Agency - Autumn Statement package |
| • Funding for: A45/46 Tollbar End, Manchester Airport link road, A453 widening, M1/M6 junction 19, A14 Kettering bypass widening • Two new managed motorway schemes: M3 (Surrey), M6 (Birmingham - Manchester) • Two schemes being accelerated: M1 J39 - J42, M25 J23 - J27 |
Alternative approaches to resolving issues along the A14 corridor |
| • Immediate investment to reduce congestion |
New Lower Thames crossing |
| • Commitment to building a new crossing - three options identified |
Mersey Gateway Bridge |
| • The Government has approved the next stage of development of the Mersey Gateway Bridge which is now in procurement • Completion of the procurement end 2013 • Scheme opening est. 2017 |
Local transport projects - funded at or before Spending Review |
| • Schemes include: Birmingham New Street, Heysham to M6 link road; Manchester Metro Link Phase 3A; Nottingham Express Transit; Midland Metro |
Local Authority major transport schemes - development pool projects |
| • Extra funding to enable all schemes to proceed, subject to assurance • 20 schemes announced in November 2011 • Further schemes to be announced in December 2011 |
Public transport |
|
|
Crossrail |
| • Spring 2012: Tunnelling commences • Spring 2014: Rolling Stock and Tunnel Depot contract let • Early 2016: Tunnelling completes • 2016: Portal works complete • Early 2018: Station Fit Outs complete • End 2018: Crossrail services commence |
Thameslink |
| • Early 2012: Contract Award for Rolling Stock • January 2018: Up to 20 Trains per hour through the core • December 2018: 24 Trains per hour through the core |
Rail infrastructure and rolling stock enhancement |
| • Support Network Rail to improve the network and to reduce disruption |
East Coast Main Line |
| • End 2011: York Holgate upgrade to the East Coast Main Line will be in service • 2014: all work complete |
Great Western Electrification |
| • 2016: Electric services to Bristol, Oxford and Newbury commence • 2017: Electric services to Cardiff commence |
Kings Cross Station improvements |
| • 2012: Western concourse will be completed • End 2013: Full completion |
Reading upgrade programme |
| • Easter 2013: Major resignalling work and construction of new platforms • 2015: Project completion (advanced one year) |
Northern rail connectivity (Liverpool-Newcastle including Northern Hub) |
| Electrify between Liverpool and Manchester via Chat Moss, Liverpool and Wigan, and Manchester and Preston via Bolton and Chorley • 2013: First section in use • 2016: Completion Ordsall Chord linking Manchester's Piccadilly and Victoria stations • 2014: Development Consent (Assumed) • 2016: Completion Manchester Victoria station improvements • 2011: Completion • Transpennine Express route electrification has been announced. Before July 2012, the Government will consider further investment in the Northern Hub |
High Speed Two |
| • December 2011: Government announces its response to the public consultation and decision on whether to proceed. • Late 2013: Submit hybrid Bill to Parliament (for London-West Midlands line) • Spring 2015: Royal assent (assumed) • 2017: Construction starts • 2026: Line opens |
Intercity Express Programme |
| • First units to be built will be tested on the network from 2015 • Introduced into revenue-earning service on the Great Western Main Line from 2016 and on the East Coast Main Line from 2018 |
London Underground capital investment programme |
| • 31 March 2012: Transport for London milestone for completing the upgrade in capacity ahead of the Olympics. |
Northern Line Extension to Battersea |
| • Support for development announced subject to commitment from a developer |
Airports |
|
|
Gatwick capital investment programme |
| • Gatwick Airport is investing around £1bn from 2008-14 in new facilities, equipment and systems • Overall, the airport has forecast that it will create some 14,000 jobs by 2021. This includes those generated by Gatwick's capital investment programme up to 2014 |
Heathrow capital investment programme |
| • BAA is investing over £5bn in Heathrow between 2008 and 2014, which includes £1bn for the construction of a new Terminal 2 to accommodate an estimated 20 million passengers every year • Terminal 2 development programme will create 35,000 direct jobs over the life of the project |
Ports |
|
|
Ports - container terminal projects |
| • 2013: London Gateway terminal and logistics centre phase 1 open |
Ports - renewable energy projects |
| • 2012: GBI grants awarded |
Local infrastructure funding programmes |
|
|
Growing Places Fund |
| • The Government has published a prospectus setting out how the Growing Places Fund will operate and inviting proposals from local partnerships |
Regional Growth Fund |
| • 31 March 2012 completion of RGF Round 1 contracting and due-diligence for infrastructure projects • 30 September 2012 completion of RGF Round 2 contracting and due-diligence for infrastructure projects. • Delivery by 2013-14 |