Check the procurement documentation

2.12  Most PFI contracts will have been let following a procurement process initiated by a notice in the relevant Official Journal (either OJEU or OJEC notice) and then in accordance with either the negotiated or competitive dialogue procedure under EU procurement law. If an authority is considering varying a contract in any material way, it is advisable to seek legal advice on any risks of challenge that might be presented under the original procurement for the specific changes being considered.