Memorandum by Dr Timothy Stone, KPMG LLP
>
[Q5]
[Q5]
More Information
Q5a-When the basis of a Private Finance contract needs to be altered post procurement because of changing client needs-for example, a bigger jail is required due to a larger than expected prison population-has this proved problematic compared to projects under traditional procurement?
Q5b-What has been the experience of PFI projects that have reverted to the public sector?