Astute Class Submarines

Astute Class Submarines

The Capability

The military requirement is for up to eight Astute Class Submersible Ship Nuclear to replace the existing Swiftsure and Trafalgar Classes of nuclear powered attack submarine. Astute Class submarines are required to perform a range of military tasks; these unique requirements are combined within the Astute design to provide global reach, endurance, covertness, sustained high speed and the ability to conduct unsupported operations in hostile environments.

Overview of Cost, Time and Performance

 

Approved

Forecast/Actual

Variation

IY Variation

Cost of Assessment Phase

£33m

£29m

-£4m

 

Cost of Demonstration & Manufacture Phase Boats 1-3

£2,233m

£3,480m

+£1,247m

+£179m

Cost of Demonstration & Manufacture Phase Boat 4

£1,279 m

£1,404m

+£125m

+£71m

Cost of Demonstration & Manufacture Phase Boat 5

£623m

£586m

-£37m

£0m

Cost of Demonstration & Manufacture Phase Boat 6

£255m

£253m

-£2m

-£1m

Cost of Support Phase - Initial Support Solution

£315m

£272m

-£43m

£0m

Cost of Support Phase - Astute Class Training Service Boats 1-3

£151m

£648m

+£497m

+£60m

Cost of support Phase - Astute Class Training Service Boat 4

£260m

£318m

+£58m

+£51m

Duration of Assessment Phase

 

69 months

 

 

In-Service Date Boats 1-3

June 2005

April 2010

+58 months

-3 months

In-Service Date Boat 4

August 2015

January 2018

+29 months

+13 months

Support Contract Go-Live - Initial Astute Support Solution

May 2007

May 2007

0 months

0 months

Support Contract Go-Live - Astute Class Training Service Boats 1-3

January 2004

March 2008

+50 months

0 months

Support Contract Go-Live - Astute Class Training Service Boat 4

December 2013

May 2015

+17 months

+35 months

Support Contract End - Initial Astute Support Solution

December 2012

December 2012

0 months

0 months

Support Contract End - Astute Class Training Service Boats 1-3

September 2026

September 2037

+132 months

0 months

Support Contract End - Astute Class Training Service Boat 4

September 2039

September 2039

0 months

0 months

 

In-year Cost and Time Variation Detail

Boat 1, First of Class, successfully completed first dive and initial series of dived trials during February and March 2010, and successfully completed full power trials and deep dive on 30 April 2010. Boat 1 was commissioned into the Royal Navy on 27 August 2010. On 22 October 2010, Boat 1 was involved in a grounding and collision incident whilst on sea trials. The submarine was repaired on the Faslane Ship Lift and left the facility on 24 November 2010. Boat 1 reached Contract Acceptance Stage 1 Platform Demonstration on 29 November 2010, (from which point it is managed as an In- Service Submarine under MOD rather than contractor direction) before returning to the sea in December 2010. Boat 2 reactor core load was completed in November 2010 with the submarine

named on 16 December 2010 and launched on 6 January 2011. It continues systems commissioning and prepares for Power Range Testing planned for late 2011, and sailing on sea trials is anticipated for Spring 2012. During 2007 to 2010 Boats 3 to 7 have been delayed due to Boat 1 holding on to scarce resource for longer to deal with the technical issues, and also due to the MOD slowing the programme down to realise early year savings.

In October 2010 the Strategic Defence and Security Review endorsed a revised build plan for the Astute class programme extending timeframes by an average of 14 months per boat. This is to sustain industry leading up to the Successor Deterrent Programme.

Risk Assessment against Defence Lines of Development

  Equipment

  Training

  Logistics

  Infrastructure

  Personnel

  Doctrine

  Organisation

  Information