Beyond Visual Range Air-to-Air Missile

Beyond Visual Range Air-to-Air Missile

The Capability

The Beyond Visual Range Air-to-Air Missile system will provide Typhoon with the capability to combat projected air-to-air threats and sustain air superiority throughout the life of the aircraft. The integration of Meteor onto Typhoon forms part of the project, with a current Initial Operating Capability of 2015. Key features of the Beyond Visual Range Air-to-Air Missile requirement include stealthy launch, enhanced kinematics (giving increased stand-off and disengagement ranges, a better ability to engage and destroy highly agile manoeuvring targets), a large no-escape zone and robust performance against countermeasures. This is a collaborative programme with: Germany; Spain; Italy; Sweden; and France.

Overview of Cost, Time and Performance

 

Approved

Forecast/Actual

Variation

IY Variation

Cost of Assessment Phase

£14m

£20m

+£6m

-

Cost of Demonstration & Manufacture Phase

£1,13 6m

£1,115m

-£21m

+£1m

Cost of Support Phase

-

-

-

-

Duration of Assessment Phase

 

55 months

 

 

Original In-Service Date

September 2011

August 2013

+23 months

0 months

In-Service Date 1

August 2012

November 2012

+3 months

+3 months

In-Service Date 2

July 2015

July 2015

0 months

0 months

In-year Cost and Time Variation Detail

There has been a three-month in-year slippage in Development outturn date owing to technical issues identified during pre- qualification activities, including the impact of a unilateral decision by one sub-contractor to change a component design for ease of production. This has delayed the start of the full qualification programme.

The programme of early integration work on Typhoon (CP270),

which began in July 2009, is proceeding on schedule, and has been expanded to mitigate delays in getting the main integration activity on contract. These latter delays represent a threat to the achievement of In-Service Date 2. Further mitigation actions are under review.

The industrial proposal for full integration (SRP14) first submitted by EF GmbH in 2009 was revised by industry in December 2010.

Risk Assessment against Defence Lines of Development

  Equipment

  Training

  Logistics

  Infrastructure

  Personnel

  Doctrine

 Organisation

  Information