Merlin Capability Sustainment Programme

Merlin Capability Sustainment Programme

The Capability

The Merlin Capability Sustainment Programme will update 30 Merlin Mk1 aircraft to overcome existing and forecast obsolescence within the Weapon System Avionics to ensure sustainment of the required capability until the planned Out of Service Date (2029). The converted aircraft will be known as Merlin Mk2.

Overview of Cost, Time and Performance

 

Approved

Forecast/Actual

Variation

IY Variation

Cost of Assessment Phase

£29m

£27m

-£2m

-

Cost of Demonstration & Manufacture Phase

£805m

£768m

-£37m

£-33m

Duration of Assessment Phase

 

34 months

 

 

In-Service Date

February 2014

February 2014

0 months

0 months

In-year Cost and Time Variation Detail

Successful achievement of first flight ahead of schedule in November 2010. The first two production aircraft are in the factory at Yeovil (aircraft 5 & 6) and conversion is underway. Initial Provisioning (IP) spares have now been contracted. Programme remains on schedule.

 

Risk Assessment against Defence Lines of Development

  Equipment

  Training

  Logistics

  Infrastructure

  Personnel

  Doctrine

  Organisation

  Information