5.2.2  Incentives and sanctions/penalties

The main incentive for the project company to achieve construction milestones is that it will not begin receiving service payments (QSP) until final completion has been achieved and certified by the independent reviewer.

The Project Agreement includes an abatement program that will reduce the QSP as a result of performance issues with the service provider, including building maintenance. This encourages the project company to ensure the facility is 'fit-for-purpose' as any building maintenance issue could result in reduced QSP.

A partly fitted out operating theatre in the new hospital.