Completion requirements as per the Project Agreement

Further to these requirements relating to the transition plan and training plan, the Project Agreement requires the project company to submit, prior to the 12 June 2008 (final completion date), the following four requirements:

•  policies and procedures manual

•  hand-over package

•  performance monitoring program

•  asset management plan.

DHS advised that all of the above requirements are expected to be completed prior to the final completion date.