7.15 The results of an evaluation should summarise:
❑ Why the outturn differed from that foreseen in the appraisal;
❑ How effective the activity was in achieving its objectives, and why;
❑ The cost effectiveness of the activity; and
❑ What the results imply for future management or policy decisions.
7.16 The results obtained should generally lead to recommendations for the future. These may include, for example, changes in procurement practice, delivery, or the continuation, modification, or replacement of a programme.