Appendix Two Changes to the Department's budgets over the spending review period

1 The table overleaf sets out the Department's final settlement for the spending review period, broken down by major programme areas. It includes selected budget lines from our sample, indicated by asterisks, where we examined the reductions made by the Department from its planned spend before the spending review. The reductions to planned spend over 2011-12 to 2014-15 are set out in absolute and percentage terms. In addition, the table contains the 2010-11 baseline used by the Treasury to calculate the total real-terms reductions by 2014-15. This is set out in the last column.

Changes to the Department budgets over the spending review period

Spending review period
(cash terms)

Change to
Planned spending
2011-12 to 2014-15

Change to Approved
budgets by 2014-15
compared with 2010-11
baseline (real terms)2

2010 -11
Baseline
(£m)

2011-12

(£m)

2012-13

(£m)

2013-14

(£m)

2014-15

(£m)

Total Over
2011-12 to 2014-15

(£m)

Absolute

Percentage

(%)

(%)

Example

Planned

a

Settlement

b

c
d

d-c

=((d-c/c)x100

=((b/1.98)-a)/a

Rail

Planned

3,260

3,250

3,083

3,236

12,829



-1,287



-10



-26

Network Rail and Passenger Rail*

Settlement

3,102

3,197

3,042

2,792

2,511

11,542

Crossrail*

Planned

625

1,254

1,227

1,054

4,160



-245



-6



341

Settlement

224

519

1,209

1,102

1,086

3,915

High Speed 2

Settlement

24

166

213

139

254

773

N/A

N/A

850

Other rail funding

Settlement

91

157

120

145

225

647

N/A

N/A

N/A

Rail total

Settlement

3,441

4,039

4,583

4,179

4,076

16,877

8

Highway Agency

Highways Agency road schemes H (including regional funding for road schemes)*

Planned

1,548

1,621

1,439

1,515

6,123


-3,861


-63


-45

Settlement

959

797

435

450

580

2,262

Highways Agency road maintenance *

Planned

850

869

892

916

3,528


-672


-19


-20

Settlement

747

833

721

647

654

2,855

Other Highways Agency funding

Settlement

1,507

856

920

893

864

3,533

N/A

N/A

N/A

Highways Agency Total

Settlement

3,212

2,486

2,076

1,990

2,098

8,650

-41

Transport for London

Transport for London grant*

Planned

2,655

2,894

3,038

3,189

3,346

12,467


-1,729


-14


-18

Settlement

2,804

2,830

2,699

2,404

10,737

Transport for London total

Settlement

2,655

2,804

2,830

2,699

2,404

10,737

-18

Local authority

Local authority road maintenance*

Planned

832

857

885

915

942

3,599


-557


15


-23

Settlement

806

779

750

707

3,042

Local authority major transport schemes*

Planned

538

561

579

598

2,275


-731


-32


-10

Settlement

433

418

364

335

427

1,544

Other local authority funding

Settlement

1,380

1,086

1,119

1,204

1,366

4,775

N/A

N/A

N/A

Local authority total

Settlement

2,645

2,310

2,261

2,289

2,500

9,361

-14

Other

Metronet

Settlement

424

352

184

-

960

N/A

N/A

N/A

Other Total

Settlement

872

1,388

1,362

1,292

873

4,915

-9

Total Settlement

12,827

13,027

13,113

12,449

11,951

-15

NOTES

1 Totals may not sum due to rounding

2 2014-15 figures are deflated by 1.098 as used by Treasury for the spending review.

3 The Transport for London grant includes both the general grant and investment grant.

Source: National Audit Office analysis Department's data