5.  Discussion of Results and Conclusions

The findings of this report are discussed below:

This study has the largest number of projects (67) included in sample set of any comparable benchmark study undertaken throughout the world. There is a good balance of Traditional and PPP projects. There is also a reasonable balance of projects according to sector -Social Infrastructure projects, Transport projects, Sustainability projects (incl. water, energy and waste) and Information Technology projects.

Conclusions:

Conclusion 1:

The sixty seven projects analysed are representative of projects where government procures major Capital assets.

 

Conclusion 2:

There are sufficient data samples in the study upon which to draw conclusions with confidence.