The following table details the results of the risk quantification using the simple evaluation technique:
(All amounts are NPV in $ millions) | NPV $m | % of risk adjusted PSC |
Total non-risk adjusted Project Cost (excl. GST) | 324.096 | 72% |
Retained risk | 10.383 | 2% |
Transferable risk | 114.267 | 25% |
Total risk adjusted Project Costs (excl. G5T) | 448.746 | 100% |