B.  SUBMISSION REQUIREMENTS

Submission requirements generally are as follows, but may be modified based on the requirements of the project.

1.  Package Submission Requirement ("SR") 1 - proponent information, general management plan and communications plan;

2.  Package SR 2 - as applicable, detailed plans for design, construction, traffic/site management, commissioning, operations, maintenance, safety audit, renewal/whole-life management (preservation and rehabilitation), condition monitoring, quality management, environmental management, LEEDTM certification, public communication, safety, project schedule, collaboration, insurance, confirmation of financial capacity and indicative financial model;

3.  Package SR2B - restated SR2 package with all components clarified, indicative financing plan and letter indicating will comply with technical requirements; and

4.  Package SR 3 - final financial model, final financing plan and final financial offer.