2.3.3  Timing of Risks

When risks are quantified, consideration must be given to the likely timing of the risks. As a result of discounting to determine the NPC, a $10 million dollar impact at the start of construction will have a greater impact in the financial model than a $10 million impact three years later during commissioning.