Capital Costs

The capital costs to construct the project are assumed to be $500 million. The owner's retained costs for their project management office is estimated to be an additional $50 million that the owner will carry regardless of the procurement approach selected.

The overall capital cost efficiency rate used to adjust the capital cost estimate, determined using the approach described in Section 3.1.1.1, is four per cent.