The OMR costs are dynamic values that change each year due to base inflation (i.e., the two and a half per cent discussed above) that is applied to the estimated cost to operate and maintain the project over 30 years. In addition, the rehabilitation component will change based on the required work in a given period. In the first year of operation, the OMR payment for this project is estimated to be $4.5 million.