The feasibility report prepared by MPV assisted in describing the expected function and form of the proposed development, particularly the aspects of configuration and functionality.
On 11 October 2004, a market briefing given to respondents to advertisements for the EOI reflected the core requirements of government. Figure 2B outlines the requirements.
Figure 2B MCCD market briefing to EOI respondents
| • Scope and objectives of the project • Key functional performance of the facility (including energy/environment) • PV structure with MCET to remain as operator • Outline risk allocations • Opportunities for commercial development • Governance structures • Evaluation criteria for bidders • Indicative development milestones |
Source: Victorian Auditor-General's Office analysis of DIIRD/MPV documents.
Our review of the EOI documentation confirmed that it contains all key deliverables specified for the project, including:
• design concepts
• functional requirements
• procurement options
• commercial development opportunities.