2.5.3  Did the procurement approach follow the rules?

We observed that the MCCD project followed a typical procurement process for a large and complex construction project.

Figure 2C Key procurement milestones for the project

Date

Procurement step

Outcome

2004

April

Government approves project

Decision to procure a PV project

 

October

EOI released

Market briefing 11 October 2004

 

December

EOI submissions received

3 parties short-listed

2005

March

Request for Proposal (RFP) released

Issued to 3 bidders

 

April

Bidder workshops

10 interactive workshops

 

August

RFP submissions received

RFP evaluation starts

 

November

RFP short list

Structured negotiations commence

2006

February

Preferred proponent selected

Public announcement

 

March

Contractual close

Contract execution

 

May

Financial close

Commence construction

Ongoing

Negotiate financial close for commercial precinct

MPV to resolve issues with commercial developer

2008

December

Construction completed

Commercial acceptance

2009

January

Commence operations

MCET as operator and Plenary as facility manager.

Source: Victorian Auditor-General's Office analysis of MPV documents.