Article 42  Modification of concessions during their term

1.  A substantial modification of the provisions of a concession during its term shall be considered as a new award for the purposes of this Directive and shall require a new concession award procedure in accordance with this Directive.

2.  A modification of a concession during its term shall be considered substantial within the meaning of paragraph 1, where it renders the concession substantially different from the one initially concluded, In any case, without prejudice to paragraph 3 and 4, a modification shall be considered substantial where one of the following conditions is met:

(a)  the modification introduces conditions which, had they been part of the initial concession award procedure, would have allowed for the selection of other applicants than those initially selected, or would have allowed for awarding the concession to another applicant or tenderer;

(b)  the modification changes the economic balance of the concession in favour of the concessionaire or

(c)  the modification extends the scope of the concession considerably to encompass supplies, services or works not initially covered.

3.  The replacement of the concessionaire shall be considered a substantial modification within the meaning of paragraph 1.

However, the first subparagraph shall not apply in the event of universal or partial succession into the position of the initial contractor, following corporate restructuring operations, insolvency or on the basis of a contractual clause of another economic operator that fulfils the criteria for qualitative selection initially established provided that this does not entail other substantial modifications to the concession and is not aimed at circumventing the application of this Directive.

4.  Where the value of a modification can be expressed in monetary terms, the modification shall not be considered to be substantial within the meaning of paragraph 1, where its value does not exceed the thresholds set out in Article 5 and where it is below 5 % of the price of the initial contract, provided that the modification does not alter the overall nature of the contract. Where several successive modifications are made, the value shall be assessed on the basis of the cumulative value of the successive modifications.

5.  Concession modifications shall not be considered substantial within the meaning of paragraph 1, where they have been provided for in the concession documents in clear, precise and unequivocal review clauses or options. Such clauses shall state the scope and nature of possible modifications or options as well as the conditions under which they may be used. They shall not provide for modifications or options that would alter the overall nature of the concession.

6.  By way of derogation from paragraph 1, a substantial modification shall not require a new concession award procedure where the following cumulative conditions are fulfilled:

(d)  the need for modification has been brought about by circumstances which a diligent contracting authority or entity could not foresee

(e)  the modification does not alter the overall nature of the concession

(f)  in case of concessions awarded by contracting authorities where any increase in price is not higher than 50% of the value of the original concession.

Contracting authorities or contracting entities shall publish in the Official Journal of the European Union a notice on such modifications. Such notices shall contain the information set out in Annex VII and be published in accordance with the provisions of Article 28.

7.  Contracting authorities and contracting entities shall not have recourse to modifications of the concession in the following cases:

(a)  where the modification would aim at remedying deficiencies in the performance of the concessionaire or the consequences thereof, which can be remedied through the enforcement of contractual obligations;

(b)  where the modification would aim at compensating risks of price increases that are the result of price fluctuations that could substantially impact the performance of a contract and that have been hedged by the concessionaire.