5.2.1  Framework and approach used

Figure 5A shows the planned timing of key stages in the procurement process for the new Royal Children's Hospital (RCH). These planned timelines were met, which was commendable, given the scale and complexity of the project and procurement task.

Figure 5A 
Planned timing of key stages in RCH procurement process

Stage

Planned timing

Expression of interest (EOI) phase

 

Release of EOI

Closing date for submission of EOI proposals

EOI evaluation and short-listing of respondents

10 May 2006 

8 June 2006

31 July 2006

Request for proposal (RFP) phase

 

Release of project brief (for RFP

Closing date for responses to RFP

11 October 2006

8 March 2007

Structured negotiation phase (SNP)

 

Release of SNP brief 

Technical and commercial workshops 

Revised proposals due 

Evaluation and clarification 

Endorsement of recommendations

1 June 2007

5 June - 6 July 2007

26 July 2007

August 2007

September 2007

Negotiation and completion phase

 

Contractual close Financial close

Financial close

November 2007

December 2007

Source: Victorian Auditor-General's Office, using data provided by DHS.

Figure 5B (overleaf) shows the major stages in developing a Partnerships Victoria project. The procurement process extends from the bidding process through to final negotiation.

Figure 5B 
Stages in developing a Partnerships Victoria project

Source: Victorian Auditor-General's Office, using data from Partnerships Victoria Contract Management Guide, page 31, figure 5.1.